10-5-22: Exterior concrete is poured for the new loading docks
10-5-22: Exterior concrete work for the new loading docks
10-5-22: Exterior concrete work for the new loading docks
10-5-22: Exterior concrete work for the new loading docks
10-5-22: Looking out the new loading dock door
10-5-22: The crane weights are removed in preparation for moving it offsite
10-5-22: Mechanical work and a new overhead door heater are installed
10-5-22: Masonry work for a new vestibule
10-5-22: Extensive ductwork is ready to be installed
10-18-22: Final exterior concrete pour
10-18-22: Final exterior concrete pour
10-18-22: Final exterior concrete pour
10-18-22: Drywall above the new restrooms
10-18-22: Painting
10-27-22: A colorful mix of electrical wire has been pulled and awaits connection
10-27-22: Ceiling painting continues
10-5-22: Exterior concrete is poured for the new loading docks
10-5-22: Exterior concrete work for the new loading docks
10-5-22: Exterior concrete work for the new loading docks
10-5-22: Exterior concrete work for the new loading docks
10-5-22: Looking out the new loading dock door
10-5-22: The crane weights are removed in preparation for moving it offsite
10-5-22: Mechanical work and a new overhead door heater are installed
10-5-22: Masonry work for a new vestibule
10-5-22: Extensive ductwork is ready to be installed
10-18-22: Final exterior concrete pour
10-18-22: Final exterior concrete pour
10-18-22: Final exterior concrete pour
10-18-22: Drywall above the new restrooms
10-18-22: Painting
10-27-22: A colorful mix of electrical wire has been pulled and awaits connection
10-27-22: Ceiling painting continues